BP Newcastle Infrastructure Project

 

Ward's role in the project was to construct a bund wall and confinement layer to prevent any environmental damage in the unlikely case of a fuel spillage. This was constructed in a fully operational fuel terminal.

 

The scope of work includes:

 

- Construct approx 1100 metres of Bund Wall, on average 2.4 metres high with an in ground footing.

- Supply and placement of approx 18,000m2 of membrane barrier and 250mm thick stabilised confinement layer.

- Other associated concrete works such as internal subdivision bunds, Tanks Aprons and Oily Water Treatment Pit.

- All associated drainage and pits.

- Earthworks including excavation reuse and removal of material.

- Maintaining temporary bunds at all times during construction.

- All associated demolition including removal of existing walls, structures and subdivision bunds.

- Installation of 400 metres of external roads and access ramps.

 

 

Client Name BP Australia
Location Cnr Industrial Drive & Elizabeth Street, Carrington NSW 2294