Sydney Cricket Ground - Hill Grandstand Early Works
Site preparation works at the Sydney Cricket Ground to enable the construction of a new grandstand on the SCG Hill.
The scope of work includes:
- Demolition and removal of the Doug Walters Stand.
- Demolition of the old score board.
- Removal of video screen, electrical kiosk and terrace seating.
- Dismantling and storage of light towers 2 and 3.
- Excavation and removal of contaminated waste.
- Excavation and removal of 20,000m3 of material.
- Propping and support of the heritage listed "Ivy Wall".
- Miscellaneous site works.
| Client Name | Sydney Cricket & Sports Ground Trust |
| Location | Gate E, Driver Ave, Moore Park |