Taxiway Primary Pit & Duct Project
Airside works within existing Sydney Airport. All works were undertaken during airport curfew hours of 11.00pm - 5.00am.
The scope of work includes:
- Installation of 220 electrical pits.
- Excavation and installation of 30,000m of electrical conduit.
- Associated backfilling.
- Reinstatement of disturbed areas including backfilling and landscaping.
| Client Name | Sydney Airports Corporation Limited |
| Location | Sydney Airport, Mascot NSW |