Taxiway Primary Pit & Duct Project

 

Airside works within existing Sydney Airport. All works were undertaken during airport curfew hours of 11.00pm - 5.00am.

 

The scope of work includes:

 

- Installation of 220 electrical pits.

- Excavation and installation of 30,000m of electrical conduit.

- Associated backfilling.

- Reinstatement of disturbed areas including backfilling and landscaping.

 

 

Client Name Sydney Airports Corporation Limited
Location Sydney Airport, Mascot NSW