MR680 Glenfield Road Upgrade

Glenfield Road Footpath

Project name: MR680 Glenfield Road Upgrade

Client: DownerMouchel

Value: $3-4 million

Location: Glenfield Road, Glenfield

Duration: 32 weeks

Commencement: October 2015

Overview: The project involves widening Glenfield Road to provide two lanes in each direction between Campbelltown Road and Brampton Avenue. RMS have deemed the upgrade necessary to:

  • ease traffic congestion
  • reduce traffic delays and improve travel time
  • improve safety for pedestrians, cyclists and motorists at the intersection and in particular on Glenfield Road

Scope of works:

  • To provide two lanes in each direction between Campbelltown Road and Brampton Avenue
  • Provide a dedicated left turn lane from Glenfield Road into Campbelltown Road
  • Upgrade the existing signalised intersection
  • Provide signalised pedestrian crossing facilities for all legs of Glenfield Road and the Campbelltown side of the Campbelltown Road intersection
  • Extend the existing dedicated right turn lane on Campbelltown Road into Glenfield Road
  • Provide a shared path along both sides of Glenfield Road
  • Upgrade existing stormwater drainage
  • Relocate and protect existing underground and overhead utilities affected by the works
  • Carry out property adjustments