AMC Carpark

Project name: AMC Carpark

Client: Downer EDI

Value: $6M

Location: Manchester Road, Auburn

Commencement: July 2014

Duration: 31 weeks

Overview: This project involved the demolition and removal of a dilapidated carpark area, including a large underground stormwater detention system.  The material below the carpark contained asbestos and was stockpiled on an adjacent site while the stormwater system was rebuilt and then replaced back into the carpark area before being capped and sealed.  The new stormwater retention system involved a series of Humes pre-cast stormtraps.