Project Name: Delhi Road Upgrade Works
Client: UrbanGrowth NSW
Value: $13M
Location: Delhi Road, North Ryde
Duration: 10 Months
Commencement: November 2017
Outline:
Ward was contracted with the high-profile task of upgrading Delhi Road. This involved the widening of the existing road into a two-lane configuration, eastbound from the M2 motorway intersection and continuing for approximately 920 meters. The project entailed the planning and implementation of traffic staging, diversion of services, as well as the construction of new pavements, drainage, and traffic signals. The works provided additional road capacity in time for the planned Epping to Chatswood rail shutdown scheduled for mid-2018.
Scope of Works: