Bluescope Steel Erskine Park

Project name: Erskine Park

Client: Bluescope Steel Pty Ltd

Value: $8M

Location: Templar Road, Erskine Park

Commencement: 2006

Duration: 26 weeks

Types of works: earthworks and concrete works

Overview: the contract involved the construction of foundations and tunnels for a new Colourbond process painting plant for BHP.

Scope of works:

  • Detail excavation
  • Temporary shoring and support
  • Construction of various reinforced concrete structures (8,000m3)
  • Installation of holding down bolts to a high degree of tolerance
  • Construction of concrete pavements