Project Name: Sydney Port Botany Terminal 3 Surface Channel Drain Replacement

Client: Hutchison Ports Sydney

Value: $7M

Location: Port Botany

Duration: 30 weeks

Commencement: December 2018

Outline:

The demolition replacement of 3km’s of surface channel drain in existing live Ports terminal.

Scope:

  • Design of cast in situ surface channel drain in accordance with Australian standards.
  • Demolition of existing failed surface channel drain.
  • Replacement of surface channel drain in accordance with approved design.
  • Make good connection detail between new drains and existing storm-water pits.