Overview: The Northern Beaches Hospital Project is located on 6.3 hectares of cleared land in Frenches Forest, Sydney. The hospital will provide a world class health care facility which includes the construction of a 488 bed, nine level hospital building (1 basement, ground floor and 7 levels above), a separate 1400 space, 10 level carpark (2 basements, ground and 7 levels above) and an on grade carpark. Ward were contracted to provide the early works for the Northern Beaches Hospital.

Scope of works:

  • Supply and installation of soil and erosion controls
  • Site clearing including woodchip and topsoil material, and demolition of remnant pavement and kerbing
  • Site levelling to required levels
  • Batters and levelling to the temporary construction carpark platform including bituminous spray seal surfacing
  • Batters and levelling to site office compound platform with a 100mm compacted road base top layer
  • Construction of north and south detention tanks, main eastern retaining wall and all associated works
  • Haul road construction