SACL Southern Terminal Expansion Enabling Works

Project Name: SACL Southern Terminal Expansion Enabling Works

Client: SACL

Value: $20M

Location: Mascot

Commencement: September 2019

Outline: 

Ward have recently been awarded a Contract by SACL for the Enabling works Southern Expansion Project.

The project is 40 week duration and includes works in a live carpark environment and airside at the International T1 Terminal.

Scope of works:

  • Realignment of existing roads through the T1 International carpark
  • Upgrade of existing Taxi/Shuttle Bus shelters and Gatehouse Building
  • Relocation/adjustment of existing utilities( Comms, electrical, water, fire water) to allow construction of new roads including airside electrical HV relocation works
  • Installation of new stormwater drainage including pump station
  • Building works associated with Arrivals Terminal
  • Various airside works including lighting columns and pavements
  • Landscaping

Ward has a long history of the successful delivery of infrastructure projects both landside and airside at Sydney International Airport.