SEL Greystanes Estate Development

Project name: SEL Greystanes Estate Development

Client: Boral Resources Pty Ltd

Value: $100M

Location: Reconciliation Drive, Prospect

Commencement: 2007

Duration: 130 weeks

Overview: Ward formed a joint venture with Burton Contractors (Burton Ward Joint Venture) to undertake the remediation of the existing Boral Quarry and convert the site into an industrial development estate.

Scope of works:

  • Bulk excavation of 2,400,000m3 of shale, dolerite and picrate
  • Blasting of 1,200,000m3 including crushing and processing
  • Construction of sewerage treatment plant, roads, and a stormwater retention system
  • Asbestos remediation
  • Removal and replacement of uncontrolled fills
  • Batter stabilisation and treatment, fencing, landscaping and maintenance