Project Name: SOPA, Site 53
Client: Mirvac Constructions
Value: $15M
Location: 2 Fig Tree Drive, Sydney Olympic Park
Duration: 10 Months
Commencement: August 2017
Outline:
Sydney Olympic Park, Site 53, was completed in two separate stages: demolition, and excavation/civil works. Stage One began with the demolition and removal of existing structured on-site, including previous buildings and USTs. Once this work is completed, Stage Two begins with the bulk excavation of 90,000 m3 of material, across an area of 8,000 m2. Civil works continued in the second stage, with the design and construction of shoring. The shoring retention system comprised of reinforced concrete piles, reinforced concrete capping beam, anchors and shotcrete. Upon completion of the bulk excavation we completed the detail excavation of lift pits, strip footings and pad footings. Ward completed the FRP to all the strip and pad footings which included column starter bars. Works around the perimeter of the site at ground level included slip lane construction and foundation piles/pile caps.
Scope of Works: