SACL Taxiway Fillet Widening Works

Sydney Airport runway widening

Project name: Taxiway Fillet Widening Works

Client: SACL

Value: $4M

Location: Sydney Airport, Mascot

Duration: 8 weeks

Commencement: January 2016

Overview: The project involved widening the corners of 5 taxiways located within Sydney Airport. The construction works could only take place between 11pm and 6am each night. Ward ran 2 full pavement crews for the project duration allowing the project to be completed in half the time and less disruption to Sydney Airport.

Scope of works:

  • Demolition of existing taxiway pavement
  • Construction of PCC Concrete pavement
  • Placement of gravel pavement
  • Asphalt works’
  • Line marking removal and re-instatement
  • AGL works to suit the new widened taxiways