Project name: The Bluff Wind Farm

Client:
Suzlon Energy Australia Pty Ltd

Value: $10M

Location: The Bluff, South Australia

Commencement: 2010

Duration: 9 months

Scope of works:

  • 25 x wind turbine generator bases, each consisting of hold down bolts, post tensioning and ground anchors, and approximately 55m3 of concrete
  • Approximately 8.5km of access roads
  • 20m x 40m crane hardstand areas at each base