Project name: UTS Thomas Street, Bulk Excavation
Client: Hansen Yuncken Pty Ltd
Value: $8.1M
Location: Corner Thomas St and Jones St, Ultimo
Commencement: February 2012
Duration: 32 weeks
Overview: Bulk excavation project at the University of Technology, Sydney. The shoring systems were required on one third of the excavation due to the high strength sandstone involved. A temporary loading platform was constructed to assist in the excavation, the last of which was done with a longreach excavator, 17m below the existing footpath level.
Scope of works: