Project name: WestConnex – St Peters Interchange Site Preparation Works

Client: Sydney Motorway Corporation

Value: $65M

Location: Alexandria Landfill Site

Commencement: June 2015

Duration: 52 weeks

Overview: The St Peters Interchange project was part of the early works for WestConnex, Australia’s largest road project, linking Sydney’s west and south-west with the city, airport and port in a 33km continuous motorway. The project involved the strategic removal of approximately 140,000 tonnes of asbestos contaminated material, removal of restricted waste, 110,000 tonnes of general solid waste, reusable sands, plastics, and timber waste.

During the project major land slip stabilisation works were conducted to the Princess Highway boundary preventing potential damage to adjoining properties.

Ward were engaged by WestConnex Delivery Authority (now Sydney Motorway Corporation) as Managing Contractor to provide a ‘value for money’ solution for the removal of the stockpiles and demolition of structures such as a dilapidated weighbridge, sound wall and concrete slabs.

Scope of works:

  • Provision of site operational services
  • Preparation and implementation of a site management plan
  • Clean up of asbestos-contaminated material, known as Stockpile 21
  • Removal of other stockpiles and miscellaneous assets from the site
  • Provision of emergency and minor works on the site