Project name: Wingham WWTP Augmentation
Client: Mid Coast Water
Value: $6M
Location: East Combined Street, Wingham
Commencement: 2007
Duration: 40 weeks
Overview: augmentation of an existing waste water treatment plant whilst in operation. The works included the construction of a new clarifying tank, sludge dewatering building, sludge tank and modification of an existing inlet works and bio reactor tank.
Scope of works:
- Bulk excavation for construction of clarifier and sludge tanks
- Installation of soil nails and shotcrete spray during bulk excavation of sludge tanks
- Construction of 2 story building to house dewatering centrifuge and polydosing equipment
- Installation of pumps, flow meters and control panels
- Testing and commissioning of all pumps, flowmeters, diffused aeration system, SCADA control and clarifying tanks works
- Extension of Inlet works, including diverting existing service and installation of new step screen and grit vortex paddle system
- Installation of turf across the site