Overview//

< BACK

Boundary Creek receives treated water from Penrith Water Resource Recovery Plant (WRRP) and St Mary’s Advanced Water Treatment Plant (AWTP) under the Replacement Flows Project. Through the increased load from these plants, in addition to flood events from the Nepean River over the past eight years, the area has been impacted causing destabilisation and erosion to the adjacent land.

Ward is responsible for the rehabilitation and stabilisation of Boundary Creek, to mitigate environmental impacts and prevent future erosion affecting neighbouring properties.

Scope of Works//

  • Bulk earthworks, including excavation, disposal of surplus spoil and importation of fill materials
  • Remediation of asbestos-contaminated soils
  • Development of temporary works designs and batter profiles
  • Creek rehabilitation, including the construction of footings, riprap, and installation of Redi-Rock, sandstone and reinforced earth retaining walls
  • Concrete and drainage works, including forming, reinforcing, and pouring V-drains, installation of stormwater pits and installation of permanent handrails
  • Backfilling embankment batters and installing scour protection
  • Comprehensive site landscaping, including planting native species and trees and creating rock pools

 

 

Ward acknowledges Traditional Owners of Country throughout Australia and recognises the continuing connections to lands, waters and communities. We pay our respect to Aboriginal and Torres Strait Islander cultures and to Elders past and present.

DESIGNED BY ZULU 8

WARD © 2026. All rights reserved.