The project was to construct four new aircraft parking bays to accommodate A380 aircraft. To achieve this, 80,000m2 of flexible and rigid pavements were built.

Scope of Works//

  • Demolition of existing pavements and structures, including the removal and disposal of demolished products
  • Bulk excavation and disposal of 80,000t of existing fill to make way for the new construction
  • Installation of stormwater lines: 350m of 1650dia stormwater line, 270m of 600dia stormwater line and 360m of concrete slot drain for
  • proper drainage of the new construction
  • Installation of hydraulic services
  • Construction of new HV sub-station, apron flood lighting, aircraft navigation system and associated in-ground cabling to support the new construction
  • Construction of 20,000m2 of concrete pavement (10,000m3)
  • Construction of 60,000m2 of flexible asphalt pavement
  • Widening of an existing bridge structure