Ward’s involvement in this project was for bulk excavation of a large site, in preparation for the development of a Stockland shopping centre.

Scope of Works//

  • Excavation of approximately 140,000m3 of material, including rock excavation and the removal of unsuitable material
  • Construction of stormwater drainage systems, including pits and pipes
  • Face stabilisation works using shotcreting for the stability of the excavated slopes
  • Detailed excavation and leveling to create the required building platforms and carpark areas
  • Line drilling works for the installation of services such as water, sewer and electrical
  • Pavement construction, including the installation of concrete works (roundabouts, splitter islands and line marking works), for safe traffic flow