Overview//
< BACKThe Taxiway Alpha and Taxiway Golf Reconstruction will renew critical airfield infrastructure to support the safe and efficient movement of aircraft across one of Australia’s busiest airports. The project focuses on extending the design life of key taxiway assets while minimising operational impacts through carefully planned staging, efficient sequencing, and strict adherence to nightly curfew hand‑back requirements.
Scope of Works//
Pavement Reconstruction
- Milling and removal of existing pavement and construction of new pavement up to 570 mm depth.
- Profiling and excavation to allow proof‑rolling of the existing subgrade.
- Supply and placement of BBFS subbase in layers ≤ 250 mm.
- Placement of temporary asphalt pavement and line marking at the end of each curfew shift to maintain safe aircraft operations.
Airfield Ground Lighting (AGL) Works
- Removal of existing AGL infrastructure.
- Installation of new AGL systems, including cabling, commissioning, and integration with airport operations.
Asphalt Surfacing
- Milling of existing asphalt surface, surface preparation including emulsion application, and placement of a new asphalt wearing course.
- Associated line marking and finishing works.
Ancillary Works
- Reinstatement of joint sealants, movement joints, and interface details with adjacent pavements and structures.
- Provision of all temporary works required to maintain MOS‑compliant, safe, and serviceable pavements during non‑curfew hours.
- Restoration of the nominated site compound at Gate 16.