Overview//

< BACK

The project involved constructing fuel storage tank foundations and containment bund walls.

Scope of Works//

  • General earthworks and preparation of the subgrade
  • Construction of five earth bund tank foundations with diameters of up to 36m
  • Installation of an HDPE liner to the underside of the containment area
  • Building 500m of 4m high containment bund walls with fully watertight joints
  • Construction and modification of associated infrastructure, including CTP, STA, fuel loading bays, and switch room
  • Other minor associated concrete pavements and works
  • Construction of four ring beam tank foundations with diameters of up to 36m