PB Roads – Project milestone
Our project team have really swung into the PB Roads project quickly and just 1 week in they have had their 1st night shift placing asphalt.
Works have involved extensive traffic management, profiling of existing pavement, trimming and proof rolling of subgrade, placement/stabilising of re-used basecourse and supply and placement of asphalt.
With good weather forecast the team are planning to continue the momentum.