The project involved the construction of a wind farm, which included the installation of wind turbine generator bases, access roads, and crane hardstand areas.

Scope of Works//

  • 25 wind turbine generator bases, each comprising hold down bolts, post tensioning, ground anchors, and approximately 55m3 of concrete
  • Approximately 8.5km of access roads
  • 20m by 40m crane hardstand areas at each base